By eight months after the entry into force of this Regulation all NEMOs shall submit to all regulatory authorities and the Agency a plan that sets out how to jointly set up and perform the MCO functions set out in paragraph 2, including necessary draft agreements between NEMOs and with third parties. The plan shall include a detailed description and the proposed timescale for implementation, which shall not be longer than 12 months, and a description of the expected impact of the terms and conditions or methodologies on the establishment and performance of the MCO functions in paragraph 2.