(23) Any costs incurred efficiently to guarantee firmness of capacity and to set up processes to comply with this Regulation should be recovered via network tariffs or appropriate mechanisms in a timely manner. NEMOs, including in performing MCO functions should be entitled to recover their incurred costs if they are efficiently incurred, reasonable and proportionate.