(106) In order to be approved by the competent authority, an establishment should have to fulfil certain requirements. Before granting the approval, the competent authority should have to verify by means of an on–site visit whether all requirements have been met. In some cases, not all conditions can be met immediately, but the remaining deficiencies do not present a significant risk to animal or public health. In such cases, it should be possible for the competent authority to grant a conditional approval, followed by another on–site visit to verify that progress has been made. In those cases, the competent authority should provide the necessary effective guidance to the operators of the establishments concerned, in order that the operator in question understands the deficiency and can plan for its successful resolution.