art_17__para_1__text_1
No later than six months after the approval of the generation and load data provision methodology established for the day-ahead and intraday time frames referred to in Article 9(6) of Regulation (EU) 2015/1222, all TSOs shall jointly develop a proposal for a single generation and load data provision methodology for delivering the generation and load data required to establish the common grid model for long-term time frames. The proposal shall be subject to consultation in accordance with Article 6. The methodology shall take into account and complement the generation and load data provision methodology according to Article 16 of Regulation (EU) 2015/1222.
← 1. · All articles · 2. →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.