Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance. ) · European Union
The TSOs of the LFC areas constituting a LFC block shall have the right, if needed, to specify internal limits, for the exchange of FRR between the LFC areas of the LFC block in the LFC block operational agreement to: avoid internal congestions due to the activation of the reserve capacity on FRR subject to the exchange of FRR; ensure an even distribution of FRR throughout the synchronous area and LFC blocks in case of network splitting; avoid that the stability of the FRP or the operational security is affected.