2.
When performing a control area adequacy analysis pursuant to paragraph 1, each TSO shall: use the latest availability plans and the latest available data for: the capabilities of power generating modules provided pursuant to Article 43(5) and Articles 45 and 51; cross-zonal capacity; possible demand response provided pursuant to Articles 52 and 53; take into account the contributions of generation from renewable energy sources and load; assess the probability and expected duration of an absence of adequacy and the expected energy not supplied as a result of such absence.
← art_105__para_1__text_1 · All articles · art_105__para_2__text_1 →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.