2.
Text with EEA relevance.
Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance. ) · European Union
The process activation structure may include: a RRP pursuant to Article 144; an imbalance netting process in accordance with Article 146; a cross-border FRR activation process in accordance with Article 147; a cross-border RR activation process in accordance with Article 148; and for synchronous areas other than CE, a time control process pursuant to Article 181.
← art_140__para_1__point_c__text_1 · All articles · art_140__para_2__text_1 →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.