7.
Text with EEA relevance.
Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance. ) · European Union
The cross-border FRR activation process shall include a fallback mechanism which shall ensure that the frequency restoration power interchange of each LFC area is zero or limited to a value for which operational security can be guaranteed.
← art_147__para_6__text_1 · All articles · art_147__para_7__text_1 →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.