art_157__para_2__point_k__text_1
Text with EEA relevance.
Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance. ) · European Union
all TSOs of a LFC block may reduce the negative reserve capacity on FRR of the LFC block, resulting from the FRR dimensioning process by concluding a FRR sharing agreement with other LFC blocks in accordance with the provisions of Title 8. The following requirements shall apply to that sharing agreement:
← (k) · All articles · (i) →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.