1.
RR providing units and RR providing groups shall comply with the following minimum technical requirements: connection to only one reserve connecting TSO; RR activation according to the setpoint received from the reserve instructing TSO; the reserve instructing TSO shall be the reserve connecting TSO or a TSO that shall be designated by the reserve connecting TSO in the RR exchange agreement pursuant to Article 165(3) or 171(4); activation of complete reserve capacity on RR within the activation time defined by the instructing TSO; de-activation of RR according to the setpoint received from the reserve instructing TSO; a RR provider shall ensure that the RR activation of the RR providing units within a reserve providing group can be monitored. For that purpose, the RR provider shall be capable of supplying to the reserve connecting TSO and the reserve instructing TSO real-time measurements of the connection point or another point of interaction agreed with the reserve connecting TSO concerning: the time-stamped scheduled active power output, for each RR providing unit and group and for each power generating module or demand unit of a RR providing group with a maximum active power output larger than or equal to 1,5 MW; the time-stamped instantaneous active power, for each RR providing unit and group, and for each power generating module or demand unit of a RR providing group with a maximum active power output larger than or equal to 1,5 MW; fulfilment of the RR availability requirements.
← Article 161 · All articles · art_161__para_1__text_1 →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.