Unless otherwise provided by the TSO, each significant grid user which is a power generating facility owner of type B, C or D power generating module shall provide the TSO, in real-time, at least the following data: position of the circuit breakers at the connection point or another point of interaction agreed with the TSO; active and reactive power at the connection point or another point of interaction agreed with the TSO; and in the case of power generating facility with consumption other than auxiliary consumption net active and reactive power.