lexiara

Article 49

Text with EEA relevance.

Unless otherwise provided by the TSO, each power generating facility owner of a power generating module which is a SGU in accordance with Article 2(1)(a) and 2(1)(e) connected to the distribution system shall provide the TSO and the DSO to which it has the connection point, with at least the following data: its scheduled unavailability, scheduled active power restriction and its forecasted scheduled active power output at the connection point; any forecasted restriction in the reactive power control capability; and as an exception to paragraphs (a) and (b), in regions with a central dispatch system, data requested by the TSO for the preparation of its active power output schedule.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.