3.

Text with EEA relevance.

Each TSO shall provide the regional security coordinator with the information necessary to detect and solve regional outage planning incompatibilities, including at least: the availability plans of its internal relevant assets, stored on the ENTSO for Electricity operational planning data environment; the most recent availability plans for all non-relevant assets of its control area which are: capable of influencing the results of the outage planning incompatibility analysis; modelled in the individual grid models which are used for the outage incompatibility assessment; scenarios on which the outage planning incompatibilities have to be investigated and used to build the corresponding common grid models derived from the common grid models for different time-frames established in accordance with Articles 67 and 79.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.