Article 85

Text with EEA relevance.

By 3 months after the approval of the methodology for assessing the relevance of assets for outage coordination in Article 84(1), all TSOs of each outage coordination region shall jointly assess the relevance of power generating modules and demand facilities for outage coordination on the basis of this methodology, and establish a single list, for each outage coordination region, of relevant power generating modules and relevant demand facilities. All TSOs of an outage coordination region shall jointly make the list of relevant power generating modules and relevant demand facilities of that outage coordination region available on the ENTSO for Electricity operational planning data environment. Each TSO shall notify to its regulatory authority the list of relevant power generating modules and relevant demand facilities for each outage coordination region in which it participates. For each internal relevant asset which is a power generating module or demand facility, the TSO shall: inform the owner of the relevant power generating module or relevant demand facility about its inclusion in the list; inform DSOs about the relevant power generating modules and the relevant demand facilities which are connected to their distribution system; and inform CDSOs about the relevant power generating modules and the relevant demand facilities which are connected to their closed distribution system.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.