11.

Text with EEA relevance.

If the Commission decision pursuant to point 10 of this Annex, requires bi-directional capacity, the Agency shall adopt a decision covering the cross-border cost allocation in line with Article 5(7) of this Regulation within three months of receipt of the Commission decision. Before taking such a decision, the Agency shall consult the regulatory authorities concerned and the transmission system operators. The three-month period may be extended by an additional period of two months where the Agency has to request additional information. The additional period shall begin on the day following receipt of the complete information.