The regulatory authorities concerned shall within six months upon receipt of the joint proposal, pursuant to Article 5(6) and (7), after consulting the project promoters concerned, take coordinated decisions on the cross-border allocation of investment costs to be borne by each transmission system operator of the project. Where the regulatory authorities concerned have not reached an agreement within that deadline, they shall inform the competent authorities concerned without delay.