2.

By 30 June 2018, and every six months thereafter during the development phase of the EES, eu-LISA shall submit a report to the European Parliament and to the Council on the state of play of the development of the EES Central System, the Uniform Interfaces and the Communication Infrastructure between the EES Central System and the Uniform Interfaces. That report shall contain detailed information about the costs incurred and information as to any risks which may impact the overall costs of the EES to be borne by the general budget of the Union in accordance with Article 64(1) and the first subparagraph of Article 64(2). Following the development of the EES, eu-LISA shall submit a report to the European Parliament and to the Council explaining in detail how the objectives, in particular relating to planning and costs, were achieved, as well as justifying any divergences.