lexiara

3.

Text with EEA relevance.

For the purposes of paragraph 4, Member States may apply to the Commission for account to be taken of electricity from renewable sources produced and consumed in a third country, in the context of the construction of an interconnector with a very long lead-time between a Member State and a third country where the following conditions are met: construction of the interconnector started by 31 December 2026; it is not possible for the interconnector to become operational by 31 December 2030; it is possible for the interconnector to become operational by 31 December 2032; after it becomes operational, the interconnector will be used for the export to the Union, in accordance with paragraph 2, of electricity from renewable sources; the application relates to a joint project that fulfils the criteria set out in points (b) and (c) of paragraph 2 and that will use the interconnector after it becomes operational, and to a quantity of electricity that is no greater than the quantity that will be exported to the Union after the interconnector becomes operational.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-10-28 · Text as adopted (Official Journal); later amendments are not incorporated in this text.