lexiara

art_16__para_4__text_1

Text with EEA relevance.

Without prejudice to paragraph 7, the permit-granting process referred to in paragraph 1 shall not exceed two years for power plants, including all relevant procedures of competent authorities. Where duly justified on the grounds of extraordinary circumstances, that two-year period may be extended by up to one year.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-10-28 · Text as adopted (Official Journal); later amendments are not incorporated in this text.