Member States shall facilitate the repowering of existing renewable energy plants by ensuring a simplified and swift permit-granting process. The length of that process shall not exceed one year. Where duly justified on the grounds of extraordinary circumstances, such as on grounds of overriding safety reasons where the repowering project impacts substantially on the grid or the original capacity, size or performance of the installation, that one-year period may be extended by up to one year.