Member States shall establish a simple-notification procedure for grid connections whereby installations or aggregated production units of renewables self-consumers and demonstration projects, with an electrical capacity of 10,8 kW or less, or equivalent for connections other than three-phase connections, are to be connected to the grid following a notification to the distribution system operator.