lexiara

art_17__para_1__text_1

Text with EEA relevance.

Member States shall establish a simple-notification procedure for grid connections whereby installations or aggregated production units of renewables self-consumers and demonstration projects, with an electrical capacity of 10,8 kW or less, or equivalent for connections other than three-phase connections, are to be connected to the grid following a notification to the distribution system operator.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-10-28 · Text as adopted (Official Journal); later amendments are not incorporated in this text.