art_15__para_5__point_a__text_1
Text with EEA relevance.
have the right to a grid connection within a reasonable time after the request, provided that all necessary conditions, such as balancing responsibility and adequate metering, are fulfilled;
← (a) · All articles · (b) →
Source: EUR-Lex (Cellar) · retrieved 2026-10-30 · Text as adopted (Official Journal); later amendments are not incorporated in this text.