lexiara

art_42__para_2__text_1

Text with EEA relevance.

The transmission system operator shall not be entitled to refuse the connection of a new generating installation or energy storage facility on the grounds of possible future limitations to available network capacities, such as congestion in distant parts of the transmission system. The transmission system operator shall supply necessary information.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-10-30 · Text as adopted (Official Journal); later amendments are not incorporated in this text.