art_42__para_3__text_1
Text with EEA relevance.
The transmission system operator shall not be entitled to refuse a new connection point, on the ground that it would lead to additional costs resulting from the necessary capacity increase of system elements in the close-up range to the connection point.
← 3. · All articles · CHAPTER VI →
Source: EUR-Lex (Cellar) · retrieved 2026-10-30 · Text as adopted (Official Journal); later amendments are not incorporated in this text.