(13) To ensure the coherence of risk assessments in a manner that builds trust between Member States in an electricity crisis, a common approach to identifying risk scenarios is needed. The ENTSO for Electricity should therefore, after consulting the relevant stakeholders, develop and update a common methodology for risk identification in cooperation with ACER, and with the ECG in its formation composed only of representatives of the Member States. The ENTSO for Electricity should propose the methodology and ACER should approve it. When consulting the ECG, ACER is to take the utmost account of the views expressed by the ECG. The ENTSO for Electricity should update the common methodology for risk identification where significant new information becomes available.