8.1
Regional coordination centres shall support the transmission system operators in the system operation region in determining the amount of balancing capacity that needs to be procured. The determination of the amount of balancing capacity shall: be performed at the day-ahead or intraday timeframe, or both; take into account possible substitutions between different types of reserve capacity with the aim to minimise the costs of procurement; take into account the volumes of required reserve capacity that are expected to be provided by balancing energy bids, which are not submitted based on a contract for balancing capacity.