Where no action plan is established within six months of identification of structural congestion pursuant to Article 14(7), the relevant transmission system operators shall, within 12 months of identification of such structural congestion, assess whether the available cross-border capacity has reached the minimum capacities provided for in Article 16(8) during the previous 12 months and shall submit an assessment report to the relevant regulatory authorities and to ACER.