art_32__para_1__text_2
Text with EEA relevance.
ACER shall monitor the implementation by the ENTSO for Electricity of network codes developed under Article 59. Where the ENTSO for Electricity has failed to implement such network codes, ACER shall request the ENTSO for Electricity to provide a duly reasoned explanation as to why it has failed to do so. ACER shall inform the Commission of that explanation and provide its opinion thereon.
← art_32__para_1__text_1 · All articles · art_32__para_1__text_3 →
Source: EUR-Lex (Cellar) · retrieved 2026-10-30 · Text as adopted (Official Journal); later amendments are not incorporated in this text.