art_37__para_1__point_p__text_1
Text with EEA relevance.
carrying out tasks related to supporting transmission system operators in the identification of needs for new transmission capacity, for upgrade of existing transmission capacity or their alternatives, to be submitted to the regional groups established pursuant to Regulation (EU) No 347/2013 and included in the ten-year network development plan referred to in Article 51 of Directive (EU) 2019/944.
← (p) · All articles · art_37__para_1__text_2 →
Source: EUR-Lex (Cellar) · retrieved 2026-10-30 · Text as adopted (Official Journal); later amendments are not incorporated in this text.