Text with EEA relevance.

For the tasks set out in this Article and not already covered by the relevant network codes or guidelines, the ENTSO for Electricity shall develop a proposal in accordance with the procedure set out in Article 27. Regional coordination centres shall carry out those tasks on the basis of the proposal following its approval by ACER.