Regional coordination centres shall report any shortcomings that they identify in the monitoring process under paragraph 1 to the ENTSO for Electricity, the regulatory authorities in the system operation region, ACER and the other competent authorities of Member States responsible for the prevention and management of crisis situations. On the basis of that report, the relevant regulatory authorities of the system operation region may propose measures to address the shortcomings to the regional coordination centres.