(a)
Text with EEA relevance.
network connection rules including rules on the connection of transmission-connected demand facilities, transmission-connected distribution facilities and distribution systems, connection of demand units used to provide demand response, requirements for grid connection of generators, requirements for high-voltage direct current grid connection, requirements for direct current-connected power park modules and remote-end high-voltage direct current converter stations, and operational notification procedures for grid connection;
← art_59__para_2__text_1 · All articles · art_59__para_2__point_a__text_1 →