Within 50 working days of the day following that of receipt of the notification under paragraph 7, the Commission may take a decision requesting the notifying bodies to amend or withdraw the decision to grant an exemption. That period may be extended by an additional 50 working days where further information is requested by the Commission. The additional period shall begin on the day following receipt of the complete information. The initial period may also be extended by consent of both the Commission and the notifying bodies.