The Commission's approval of an exemption decision shall expire two years after the date of its adoption in the event that construction of the interconnector has not started by that date, and five years after the date of its adoption if the interconnector has not become operational by that date, unless the Commission decides, on the basis of a reasoned request by the notifying bodies, that any delay is due to major obstacles beyond the control of the person to whom the exemption has been granted.