However, where an Interreg programme covers support from an external financing instrument of the Union, the Member State hosting the prospective managing authority shall submit the Interreg programme to the Commission not later than nine months after the adoption by the Commission of the relevant multi-annual strategy documents provided for in Article 10(1) or in accordance with the respective basic legislative act of that external financing instrument of the Union.