art_63__para_2
2. Expenditure shall be eligible for a contribution from the Funds if it has been incurred by a beneficiary or the private partner of a PPP operation and paid in implementing operations, between the date of submission of the programme to the Commission or from 1 January 2021, whichever date is earlier, and 31 December 2029. For costs reimbursed pursuant to points (b), (c) and (f) of Article 53(1), the actions constituting the basis for reimbursement shall be carried out between the date of submission of the programme to the Commission or from 1 January 2021, whichever is earlier, and 31 December 2029.
← art_63__para_1 · All articles · art_63__para_2__para →
Source: EUR-Lex (Cellar) · retrieved 2026-10-28 · Text as adopted (Official Journal); later amendments are not incorporated in this text.