ensure, subject to the availability of funding, that a beneficiary receives the amount due in full and no later than 80 days from the date of submission of the payment claim by the beneficiary; the deadline may be interrupted if information submitted by the beneficiary does not allow the managing authority to establish whether the amount is due;