(b)
ensure, subject to the availability of funding, that a beneficiary receives the amount due in full and no later than 80 days from the date of submission of the payment claim by the beneficiary; the deadline may be interrupted if information submitted by the beneficiary does not allow the managing authority to establish whether the amount is due;
← (ii) · All articles · (c) →
Source: EUR-Lex (Cellar) · retrieved 2026-10-28 · Text as adopted (Official Journal); later amendments are not incorporated in this text.