6. No later than 45 days following the receipt of a permit-granting application related to a Strategic Project, the single point of contact concerned shall acknowledge that the application is complete or, if the project promoter has not sent all the information required to process an application, request the project promoter to submit a complete application without undue delay, specifying which information is missing. Where the application submitted is deemed to be incomplete a second time, the single point of contact concerned shall not request information in areas not covered in the first request for additional information and shall be entitled only to request further evidence to complete the identified missing information. The date of the acknowledgement referred to in the first subparagraph shall serve as the start of the permit-granting process.