1. Where an environmental impact assessment is required for a Strategic Project in accordance with Articles 5 to 9 of Directive 2011/92/EU, the relevant project promoter shall request, no later than 30 days after the notification of the recognition as a Strategic Project and before submitting the application, an opinion from the single point of contact concerned on the scope and level of detail of the information to be included in the environmental impact assessment report under Article 5(1) of that Directive. The single point of contact concerned shall ensure that the opinion referred to in the first subparagraph is issued as soon as possible and within a period of time not exceeding 45 days from the date on which the project promoter submitted its request for an opinion.