10. In exceptional cases, where the nature, complexity or size of an application so require or where the number of applications received before a particular cut-off date is too high to allow for the processing of applications within the time limit referred to in paragraph 9, the Commission may, on a case-by-case basis and no later than 20 days before the expiry of the time limit referred to in paragraph 9, extend that time limit by a maximum of 90 days. In that event, the Commission shall inform the project promoter in writing of the reasons justifying the extension and of the time limit for the decision.