Recital 21
(21) To structure the process, the Commission should organise an open call with regular cut-off dates, corresponding to meeting dates of the Board, for project promoters to apply for recognition of their projects as Strategic Projects. To provide clarity for project promoters regarding their applications for Strategic Projects, the Commission should comply with a deadline for its decision on whether to recognise a project as strategic. To accommodate particularly complex cases or a high number of applications at one cut-off date, the Commission should be able to extend that deadline once. It should share its assessment with the Board before its meeting and should take the Board’s opinion into account in its decision on whether to recognise a Strategic Project.