If adverse impacts on the site’s integrity have been identified during the appropriate assessment or cannot be ruled out, the plan or project in question cannot be approved. However, depending on the degree of impact identified, it may be possible to apply mitigation measures to avoid these impacts or reduce them to a level where they will no longer adversely affect the integrity of the site. See the Article 6 Guide – section 4.6.6.