Instruments for stocking areas and compensation measures which have already been established in other contexts also show that an earlier implementation of the measures is possible and can be put into practice from a planning point of view (cf. e.g. AMMERMANN et al. 1998, BUNZEL & BÖHME 2002). As a supplementary possibility here, agreements could also be made between the project operator and the operator of a land reserve. These agreements would allow for the measures carried out to be taken over by the operator of the land reserve and financially compensated in the unlikely event that the project could not, for some unforeseen reason, be realised after all.