An effective way to prevent conflicts with Natura 2000 sites and EU protected species and habitats is to consider the environmental consequences of new developments early on at strategic planning level. This can be done through a regional or national development plan for sectoral activities (e.g. in the energy sector, transport, extractive activities, aquaculture) or through land-use or other spatial plans. Having a strategic plan makes it possible to integrate environmental conditions and requirements, in particular those related to nature conservation, at an early planning stage so that the risk of potential conflicts later on at project level can be avoided or minimised and to determine the feasibility and means of implementing individual developments accordingly.