COMMISSION NOTICE Guidance on the interpretation and application of Directive 2011/83/EU of the European Parliament and of the Council on consumer rights · European Union
A distinction should be made between construction contracts and service contracts related to the construction. In case C-208/19 NK the Court noted that the exception under Article 3(3)(f) would not apply to a contract between an architect and a consumer, according to which the former is required to prepare the designs for the construction of a new building. Although the design precedes construction works, it is a separate process, and in fact there is no certainty that the building will be constructed at all (35).
← — · All articles · sec_1_7_1__para__4 →
Source: EUR-Lex (Cellar) · retrieved 2026-09-25 · Text as adopted (Official Journal); later amendments are not incorporated in this text.