Section 10(4)
A variation notice served under subsection (2) above shall also— require the holder of the authorisation, within such period as may be specified in the notice, to notify the authority what action (if any) he proposes to take to ensure that the process is carried on in accordance with the authorisation as varied by the notice; and require the holder to pay, within such period as may be specified in the notice,— in a case where the enforcing authority is the Environment Agency or SEPA, the charge (if any) prescribed for the purpose by a charging scheme under section 41 of the Environment Act 1995; or in any other case, the fee (if any) prescribed by a scheme under section 8 above.