lexiara

Schedule 19, paragraph 5(1)

WRA 1991
Water Resources Act 1991 · United Kingdom

As soon as practicable after a compulsory works order has been made, the appropriate agency shall— publish a notice of the making of the order, at least once in each of two successive weeks, in one or more newspapers circulating in each relevant locality; and not later than the date on which that notice is first published— serve a copy of the notice on every person on whom the appropriate agency was, by virtue of paragraph 1(1)(c)(i) above, required to serve a copy of the notice with respect to the application for the order; and in the case of an order authorising the stopping-up or diversion of a footpath, bridleway or restricted byway, cause such a copy, together with a plan showing the general effect of the order so far as it relates to the footpath, bridleway or restricted byway, to be displayed in a prominent position at the ends of the appropriate part of the path or way.

· All articles ·