Schedule 13, paragraph 9(6)

EA 1995
Environment Act 1995 · United Kingdom

Where the mineral planning authority receive an application under this paragraph in relation to a dormant site or an active Phase I or II site they shall determine the conditions to which each relevant planning permission relating to the site is to be subject; and any such permission shall, from the date when the conditions to which it is to be subject are finally determined, have effect subject to the conditions which are determined under this Schedule as being the conditions to which it is to be subject.