Section 4
PA 2023
Procurement Act 2023 · United Kingdom
For the purposes of this Act, the “estimated value” of a contract is its value for the time being estimated by a contracting authority. A contracting authority that estimates the value of a contract must do so in accordance with Schedule 3. A contracting authority must not exercise a discretion in connection with estimating the value of a contract with a view to securing that any requirement of this Act does not apply in relation to the contract.