Section 54(4)
PA 2023
Procurement Act 2023 · United Kingdom
A tendering period set under this Part must equal or exceed the shortest minimum period specified in an entry in the second column of the following table that corresponds with an entry in the first column that applies to the circumstances of the case— The contract— and is subject to a negotiated tendering period being awarded is a utilities contract, or is being awarded by a contracting authority that is not a central government authority, The contract— and tenders may be submitted only by preselected suppliers being awarded is a utilities contract, or is being awarded by a contracting authority that is not a central government authority,